The Supreme Judicial Court (SJC) is slated to hear oral argument in G4S Technology LLC v. Mass. Technology Park Corp. on Monday, March 5, 2017 – a case with significant implications for construction litigation.

The dispute arises out of a $45 million public works project to build a 1200-mile fiber optic network bringing high speed Internet access to western Massachusetts. Appellee Massachusetts Technology Park Corporation (MTPC), a state development agency, awarded the contract to design and build the fiber optic network to Appellant G4S Technology LLC (G4S).
Continue Reading Oral Argument Preview: G4S Technology LLC v. Mass. Technology Park Corp.

In a recent decision, Elec. Contractors, Inc. v. Fid. & Deposit Co. of Maryland, No. 3:13-CV-00514 MPS, 2015 WL 1444481 (D. Conn. Mar. 30, 2015), the United States District Court for the District of Connecticut dismissed on summary judgment a subcontractor’s claims for delay damages against the general contractor on a construction project (“Project”)