For years, general contractors and trade contractors have faced very strict “no damages for delay” clauses on New York State construction projects. The tides are changing.  If signed into law, S. R. 06686, Reg. Sess. 2017-2018 (NY 2017) will require public entities to allow contractors, subcontractors and suppliers to recover for costs associated with project delays to the extent the delays were caused by the entity’s actions or inactions. Public entities would include, without limitation, any state agency, department, board, bureau, municipal corporation, school district or any instrumentality or public subdivision of the State of New York.
Continue Reading Will Strict “No Damages for Delay” Clauses Be Outlawed on New York Public Construction Projects? Stay tuned.