Our readers may recall that Public Act No. 15-28 was signed by the Governor back in 2015, subjecting the State of Connecticut and its political subdivisions to a statute of limitations for asserting actions and claims arising out of “construction-related work.” The law became effective as of October 1, 2017. “Construction-related work” is defined in the Act to include the design, construction, construction management, planning, construction administration, surveying, supervision, inspection or observation of construction of improvements to real property. Notably, it applies not only to the State, but also its subdivisions such as cities, towns, and other entities like school districts.

The limitations period set forth in the Act is 10 years from the date of substantial completion of a given improvement. The 10 year limitations period applies going forward to improvements to real property substantially completed on or after October 1, 2017. For improvements substantially completed before October 1, the limitations period runs to October 1, 2027. Prior to the Act, the State and its political subdivisions were generally not subject to any statutes of limitations for such claims due to the legal doctrine of nullum tempus occurrit regi, which provides that a state is not subject to statutes of limitations unless it specifically consents to be. Literally translated, it means that “no time runs against the king.”
Continue Reading Tic Toc Tic Toc: The Clock Is Running on Construction and Design Claims by the State of Connecticut Beginning October 1, 2017