A common provision often deleted from the standard form AIA documents is the provision in the AIA A201 General Conditions requiring an Initial Decision Maker (IDM) for claims between the contractor and owner. In the A201, the contracting parties have the option of naming their own IDM for the project. If an IDM is not
CONTRACTS
Connecticut Court Clarifies a Limit on Payment Bond Claims for Public Projects
By Bill Wilson on
Posted in Construction contracts and claims
In All Seasons Landscaping, Inc. v. Travelers Casualty & Surety Co., No. DBD-CV21-6039074-S, 2022 WL 1135703 (Conn. Super. Ct. April 4, 2022) the plaintiff, a subcontractor on a state project, commenced a lawsuit against the surety who issued a payment bond on the project two years after the subcontractor last performed any original contract work…